logo

Quản lý dự án công nghệ thông tin

Describe the Project Management Body of Knowledge (PMBOK) area called project cost management. Develop a Gantt chart. Develop a project network diagram using the activity on the node (AON) technique. Identify a project’s critical path and explain why it must be controlled and managed. Develop a PERT diagram. Describe the concept of precedence diagramming and identify finish­to­start, start­to­start, finish­to­finish, and start­to­finish activity relationships Describe the Project Management Body of Knowledge (PMBOK) called Project Cost Management Describe the various costs for determining the project’s budget. Define what is meant by the baseline project plan. ...
 Describe the Project Management Body of Knowledge (PMBOK)  area called project cost management.  Develop a Gantt chart.  Develop a project network diagram using the activity on the node  (AON) technique.  Identify a project’s critical path and explain why it must be controlled  and managed.  Develop a PERT diagram.  Describe the concept of precedence diagramming and identify  finish­to­start, start­to­start, finish­to­finish, and start­to­finish activity  relationships  Describe the Project Management Body of Knowledge (PMBOK)  called Project Cost Management  Describe the various costs for determining the project’s budget.  Define what is meant by the baseline project plan.  Activity definition  Activity sequencing  Activity duration estimation  Schedule development  Schedule control  Resource planning Cost estimating Cost budgeting Cost control - 0.0 Husky Air Project + 1.0 Conceptualize & Initialize Project + 2.0 Develop Charter & Plan + 3.0 Analysis + 4.0 Design + 5.0 Construct + 6.0 Test + 6.1 Test Plan - 6.2 Test Results Report 6.2.1 Review test plan with client 6.2.2 Carry out test plan 6.2.3 Analyze results 6.2.4 Prepare test results report and presentation 6.2.5 Present test results to client 6.2.6 Milestone: Client signs off on test results 6.3 Milestone: Testing completed + 7.0 Implementation + 8.0 Close Project + 9.0 Evaluate Project Success  Put it all together to determine the start and end  dates for the project  Iterations may be necessary  A realistic project schedule is the goal!  Project Management Tools ◦ Gantt Charts ◦ Project Network Diagrams  Activity on the Node (AON)  Critical Path Analysis  Program Evaluation and Review Technique (PERT)  Precedence Diagramming Method (PDM) Activity Description Estimated Predecessor Duration (Days) A Evaluate current technology 2 None platform B Define user requirements 5 A C Design Web page layouts 4 B D Set-up Server 3 B E Estimate Web traffic 1 B F Test Web pages and links 4 C,D G Move web pages to 3 D,E production environment H Write announcement of 2 F,G intranet for corp. newsletter I Train users 5 G J Write report to management 1 H,I Possible Paths Path Total Path 1 A+B+C+F+H+J 18 2+5+4+4+2+1 Path 2 A+B+D+F+H+J 17 2+5+3+4+2+1 Path 3 A+B+D+G+H+J 16 2+5+3+3+2+1 Path 4 A+B+D+G+I+J 19* 2+5+3+3+5+1 Path 5 A+B+E+G+I+J 17 2+5+1+3+5+1  Longest path  Shortest time project can be completed ◦ Zero slack (or float)  The amount of time an activity can be delayed before it delays  the project  Must be monitored and managed! ◦ Project manager can expedite or crash by adding  resources ◦ Fast tracking – running activities in parallel which were  originally planned as sequential ◦ The CP can change ◦ Can have multiple CPs  Program Evaluation and Review Technique  Developed in 1950s to help manage the Polaris  Submarine Project  Developed about the same time as the Critical  Path Method ◦ Often combined as PERT/CPM   Employs both a project network diagram with a  statistical distribution Activity Predecessor Optimistic Most Likely Pessimistic Expected Estimates Estimates Estimates Duration (Days) (Days) (Days) (a+4b+c) 6 A None 1 2 4 2.2 B A 3 5 8 5.2 C B 2 4 5 3.8 D B 2 3 6 3.3 E B 1 1 1 1.0 F C,D 2 4 6 4.0 G D,E 2 3 4 3.0 H F,G 1 2 5 2.3 I G 4 5 9 5.5 J H,I .5 1 3 1.3  Lead is starting the next task before the first task  is complete  Example: Begin installing the operating systems when half of  the PCs are set up  Lag (or negative lead) is the adding of a buffer of  time before the next task begins  Example: Once the walls have been painted, wait one day  before laying the carpet so that the walls have had a chance  to dry 1. Define what resources will be needed to perform  the work  2. Determine the quantity of resources that are  needed  3. Define the cost of using each resource  4. Calculate the cost of the task or activity  5. Ensure that the resources are leveled, that is,  resources have not been over allocated  assigned to more than one task scheduled at the  same time  Direct Costs ◦ The direct cost of labor or other resources  Indirect Costs ◦ The cost for covering such things as rent, utilities, insurance, etc.  Sunk Costs ◦ Costs incurred prior to the project such as a project that has  been restarted after a failed attempt  Learning Curve ◦ Often have to “Build one and throw it away” to understand a  problem or a new technology  Prorated Costs ◦ The idea that there is a cost associated with using a resource  Reserves ◦ Contingency funds to be used at the discretion of the project  manager  The project schedule and budget may require  several iterations before it is acceptable to the  sponsor, the project manager, and the project  team   Once the project schedule and project plan are  accepted, the project plan becomes the baseline  plan.  Once accepted, the project manager and project  team have the authority to execute or carry out the  plan. 
DMCA.com Protection Status Copyright by webtailieu.net